Remove and clean bars
Clean pilot assembly - adjust if necessary
Clean and inspect heat exchanger and flueways
Clean ignition system - adjust if necessary
Clean flame failure system - replace if necessary
Check all joints and seals
Re-assemble boiler - check operation and flame picture
Check gas pressure to manufacture's recommendations
- adjust if necessary
Check all electrical controls i.e. programmer/time switch
and thermostats for correct operation and safety
Check circulating pump(s) for correct operation
Check plant room ventilation
Check fire valve for correct operation and condition of
firewire, if fitted
Test and check boiler plant for correct operation
Controls re-set to customer's requirements
Note and list any replacement parts and/or further work required
Carry out full gas soundness
Check header tank and cold water supply tank for correct operation
Leave boiler plant room in clean and tidy condition
Please note that this procedure will vary from one appliance
to another

Copyright © 2003 ULTRA-WARM LTD Legal Notice